1
- Preliminary Drawings . (design
concepts)
2 -
Contract drawings.
3 -
Working drawings . (actual construction)
4 -
Shop drawing. (between design and construction)
1
- Preliminary Drawings
- Preliminary drawings prepared to the degree that owner can visualize the total project.
- Preliminary drawings complete enough to allow the preparation of a realistic budget estimate.
- Anything that can contribute to a more complete understanding of the client shall be considered.
2
Contract drawings.
- The contract drawings are used as an essential part of the contract.
- Keep a set on the job with all changes and revisions posted.
3
Working drawings .
- Based on the design presented in the preliminary drawings, approved by owner.
- The Working Drawings include all the information needed to obtain a building permits
- The approved design is not changed but it is further developed, defined, and improved.
- Working drawings together with specifications give complete picture of the project.
- Used by several groups of people. Hence should be prepared to meet the requirement of each group.
4
Shop drawing.
- A shop drawing is a drawing or set of drawings produced by the contractor, supplier, manufacturer, subcontractor, or fabricator.
- Shop drawings are reviewed by the design professional.
- Approval of the shop drawings by Design Professional is a restricted approval (check against the intent of design drawings only)
- Shop drawings are actually an extension and further development of working drawings.
- Shop drawings do not change the intent of the working drawings.
- Prepared by subcontractors or material suppliers. In some cases also by the general contractor.
- Shop drawings are provided for works such as: Installation and fabrication, structural steel, mill work, metal windows and doors, pipes and pumps and etc.....
- Responsibility of errors and omissions in shop drawings lies with the contractor/subcontractor.
- Timely approval of shop drawings is of prime importance!
- Shop drawings approval may effect project schedule, if not submitted on time.
- Record shop drawings in contractor’s submittal log.
- Shop drawings should be stamped and dated immediately upon receipt.
5
As-built drawings
- Most specifications require that the contractor refrain from ordering material until the shop drawings are approved officially. (IN WRITING)
- Usually these are “location drawings” to which the owner may refer for maintenance and repairs.
- Working drawings show ”proposed” locations for pipes, valves, man holes, etc....., as built drawings show “actual” locations, of installations.
- Usually general contractor or sub-contractors prepare as-built drawings.
- Requirement for as-builtdrawing, should be included in bidding documents.
- If not included in the contract documents, and if required legally, can be added by issuing a change order.
- The term as-built drawings in unpopular because of some legal difficulties with some design professionals.
Legal Requirements :
- Seal of design professional.
- Seal of surveyors for site drawings.
- Seal of AE for general project drawings.
- Seal on various supporting drawings by related design professional e.g.. Landscape architect, mechanical/electrical engineer.
- Each drawing sheet must contain a title block with:
- Number of project and sheet
- Date of drawings
- Type of information (plan, section)
- Name of design professional
- Checked by, date checked, etc....
No comments:
Post a Comment